At Full Scale: capital repairs on the international highway between Lviv and the “Rava-Ruska – Hrebenne”
At Full Scale: capital repairs on the international highway between Lviv and the “Rava-Ruska – Hrebenne” border checkpoint is underway across multiple sections, covering the full width of the road.
Over 330 workers are operating on the site in two shifts, with 150 pieces of machinery involved.
This is the main route from Kyiv to Warsaw and part of the Trans-European Transport Network (TEN-T). The length of our section under repair (from the village of Volia-Vysotska to the border crossing) is 33.4 km.
Before the war, the EBRD carried out a road safety audit, an economic feasibility study, and environmental and social assessments. In 2020, Ukraine and the Bank signed a financing agreement covering a number of projects, including the overhaul of the M-09.
During the war, the project became even more critical – traffic volume increased, and the road’s condition worsened.
Project scope includes: