N-31 Highway Construction Resumes: First Cement-Treated Crushed Stone–Sand Base Layer Laid with the Vögele Super 2100-3
Construction is progressing on the N-31 Dnipro – Tsarychanka – Kobeliaky – Reshetylivka highway, where we are completing the road base on the first 800-metre section adjacent to a tunnel-type underpass designed for agricultural vehicles.
Before the full-scale war, the base layers made of blast furnace (steelmaking) slag had already been completed on this section.
Following the resumption of construction works, we placed a crushed stone–sand mixture (CSM) base layer. We are now laying the final pavement foundation layer – cement-treated crushed stone–sand mixture (CTCSM).
To pave this layer, we are using the flagship Vögele Super 2100-3 paver, specifically designed for the construction of motorways, airport runways, and large industrial facilities.
The paving width is 11 metres.
Placing the material across both carriageway lanes in a single pass ensures the strength, durability, and structural integrity of the pavement foundation.
Our next update will cover the following stage of construction – placement of the base asphalt concrete course.
PROJECT BACKGROUND
Construction of the second phase of the project – a 30-kilometre section extending from the Dnipro–Donbas Canal to the border with Poltava Region – was suspended after the outbreak of the full-scale war.
As a result, traffic has continued to use the existing route – a narrow, deteriorated road passing through local communities.
The condition of the existing road has become critical and it has long required complete reconstruction.
In 2021, our company completed a substantial portion of the works on the second construction phase:
Considering the substantial amount of work already completed, it is now possible to make every effort to partially open the second construction phase of the N-31 highway to traffic before the end of the year, although certain traffic restrictions will remain in place.
Construction activities have therefore resumed. The company is currently:
PROJECT INFORMATION
The new construction of the N-31 expressway between the Dnipro–Donbas Canal and the border with Poltava Region includes:
• construction of 14 engineering structures, including agricultural underpasses, monolithic tunnels connecting local communities, grade-separated interchanges, and overpasses;
• relocation of existing utility networks;
• construction of two pavement foundation layers using slag aggregate;
• construction of a crushed stone–sand mixture (CSM) base layer;
• construction of a cement-treated crushed stone–sand mixture (CTCSM) base layer;
• construction of a three-layer asphalt concrete pavement;
• construction of stormwater treatment facilities;
• installation of stormwater drainage systems;
• installation of variable message signs and weather monitoring stations;
• installation of lighting at interchanges;
• construction of access roads and junctions;
• installation of safety barriers;
• installation of road signs;
• application of road markings;
• landscaping of adjacent areas, including the planting of approximately 5,500 trees.
• installation of Weigh-in-Motion (WIM) systems on both carriageways;
• installation of noise barriers.
The pavement structure will incorporate nearly half a million tonnes of slag supplied by metallurgical plants in Dnipropetrovsk Region.
The most technically challenging element of the project is the construction of an almost 600-metre viaduct crossing the meandering Oril River within a protected nature reserve.