New Stormwater Drainage System!
The capital repair of the international highway section between Lviv and the Rava-Ruska—Hrebenne border crossing is ongoing. Currently, the works permitted during the winter period are being carried out:
•
Installing a stormwater drainage system within settlements. Previously, there was no organized water drainage, which led to waterlogging and the deterioration of the pavement structure. In total, we plan to lay about 5 km of drainage networks.
•
Dismantled the last of six bridges; preparations for the foundation installation are underway.
This is the main route from Kyiv to Warsaw and part of the Trans-European Transport Network (TEN-T). The length of our section under repair (from the village of Volia-Vysotska to the border crossing) is 33.4 km.
Before the war, the EBRD carried out a road safety audit, an economic feasibility study, and environmental and social assessments. In 2020, Ukraine and the Bank signed a financing agreement covering a number of projects, including the overhaul of the M-09.
During the war, the project became even more critical – traffic volume increased, and the road’s condition worsened.
Project scope includes: