New Road Markings and 2 More Kilometers Repaired: Wrapping Up Routine Maintenance on the Morshyn Bypass!
Our company began working on the H-10 highway (Stryi – Ivano-Frankivsk – Chernivtsi) near Morshyn back in 2024 with the repair of the bridge over the Berezhnytsia River.
This spring, during emergency repairs, we restored approximately 7 km of the road by laying a cement-treated crushed stone-sand mixture (CSSM) base and a layer of fine-grained asphalt concrete. This autumn, we were able to continue our work as part of routine maintenance.
Overall, the project aims to rehabilitate the entire H-10 section from Stryi to the Ivano-Frankivsk Oblast border. However, this year’s funding allows us to construct the road base and lay new pavement on only two sections totaling 2 km in length.
Key stages of work:
• Milling to a depth of 4.5 cm;
• Laying a 15 cm layer of M-20 crushed stone-sand mixture;
• Paving a 10 cm layer of coarse-grained asphalt concrete;
• Applying road markings.
We have received many questions from drivers on social media regarding road markings. Applying them is included in the current maintenance scope. Soon, all sections restored this year will feature pedestrian crossings, centerlines, and edge lines made of durable cold-applied plastic!
The photo shows the process of laying the crushed stone-sand mixture.
The treated CSSM layer bears the primary traffic load, absorbing wheel pressure and distributing it evenly over a wide area. A sign of high-quality cement-treated CSSM paving is a dense, monolithic layer free of loose spots, material segregation, or visible rutting after the compaction equipment passes.