We put into operation the first section of the M3 highway “Kyshiniv-Djurdzhulesti” in Moldova
The project of construction and reconstruction of the M-3 highway is being completed. In the coming days, we plan to commission the first section, 54 km long. The second section, 21 km long, will be completed by mid-December.
The delivery of the third section, 11 km long, is scheduled for the spring of 2023. The road is open, but the installation of edge drainage trays, strengthening of roadsides and slopes is still ongoing.
We would like to remind you that work on the 85-kilometer M3 highway “Kyshiniv-Djurdzhulesti” began in 2019. “Automagistral-Pivden” has created a production base in the city of Vulkanesti, where an asphalt concrete plant and a soil mixing plant are located. During 2022, the company built 7 kilometers of road, and on another 4 kilometers, the expansion and installation of auxiliary road structures was carried out.
The project in Moldova provided for the creation of all the necessary accompanying infrastructure of the highway – these are new, modern car pavilions, lighting, pedestrian paths, parking lots.
The first section of the project (km 96+800 — km 151+200) with a length of 55 km includes nine bridges.
Two other sections: km 151+200 — km 171+290 and km 179+650 — km 190+750) In total, “Automagistral-Pivden” restored almost 85 km of this highway in three years. The project is financed by the EBRD.