The pace of work on the restoration of the M3 highway in Moldova is increasing

Since the beginning of summer, the company has completed a large volume of work on the last sections of new construction and reconstruction in Moldova.

The structures of two bridges at 151 and 170 kilometers have been completed: it remains to arrange a layer of road clothing, install a guard rail.

Ahead of work on 3 kilometers of new construction and 2 kilometers of reconstruction, which involves the expansion of the road.

It seems that the plots are relatively small, but the complexity of the landscape causes a large amount of work. The height of the embankment in some places reaches 12 meters. Accordingly, the project also includes works on strengthening the slopes, installation of the drainage system. Suffice it to say that the company needs to install 12 kilometers of concrete trays!

Since the activation of works in April, 39 units of equipment were additionally moved to Moldova. Another 11 units are expected to arrive. Currently, more than fifty trucks and more than one hundred units of specialized equipment are involved in the project.

We would like to remind you that work on the 85-kilometer stretch of the M3 highway “Kyshiniv-Djurdzhulesti” began in 2019. Our company even built a production base in the city of Vulkanesti, where an asphalt concrete plant and a soil mixing plant are located.

Currently, the first section of the project (km 96+800 — km 151+200) with a length of 55 km, including nine bridges, is almost completed.

On two other sections (km 151+200 — km 171+290) and km (179+650 — km 190+750), where reconstruction is planned, active construction is still ongoing.

This year, 7 kilometers of roads need to be built “from scratch”, and an additional 4 kilometers are planned for extension and auxiliary road structures.

In addition, work on two bridges remains.
It is planned to complete the work by October 2022.
Our project in Moldova involves the creation of the accompanying infrastructure of the highway – new, modern car pavilions, lighting, pedestrian paths, parking lots.
The successful completion of the Chisinau-Dzurgiulesti route is the debut of our company on the European market. We are already working on receiving new orders from other European countries.