In Sumy Oblast, the second stage of repair of the bypass road network around the bridge in Chumakovo across the Seim River is underway

The bridge was completely destroyed by Russian troops during the deoccupation of the region. The detour route on local roads is approximately 27 kilometers. The entire flow of transit traffic from the T-19-10 route (Konotop-Buryn-Chumakove) moves exactly this way, passing a small surviving town on the way. The local network can no longer withstand the load, the coverage is rapidly collapsing. Even before the war, it was planned to carry out a major repair of the bypass, after which to proceed to a major repair of the bridge over the Seim with a total length of 250 meters. Our company had to do the work. But the war began.
Work on the repair of the bypass route began in mid-June. This is milling, correction of the profile with the addition of new material (ShPS) and arrangement of a layer of fine-grained asphalt concrete.
The length of the first section was 2.7 km.
Currently, work is already being carried out on the second section of the road of local importance О190205 Buryn-Zarichne, 2.3 km long.
At the same time, our bridge builders are participating in the restoration of one of the region’s bridges on the T-19-09 highway. We are installing a monolithic slab 14 cm thick, at the next stage we plan to install monolithic pavement blocks, an 11 cm thick asphalt concrete coating and a barrier fence. In total, 5 bridges on roads of state importance were destroyed in Sumy Oblast. So far, it is planned to restore two of them.