In Chernihiv region, we are planning to open the M-01 highway
This is the main route connecting the regional center with Kyiv.
All problematic sections of the route, which hindered traffic, finally became “passable”.
In particular, on the southern approach to Chernihiv, our company completed the approach near the destroyed bridge. The total length of the access road is more than 800 meters.
A small bridge near Topchiivka has also been restored: new floor slabs have been installed, a layer of asphalt concrete has been installed, work on the installation of a barrier fence is ongoing.
The bridge near the neighboring Ivanivka has been dismantled. Work is just beginning on it, but a detour has been organized, where we laid a layer of asphalt concrete last week.
At the same time, it is worth noting that the M-01 will have a weight limit of up to 10 tons.
The regional road P-69 Kyiv-Chernihiv, which was planned to be completely repaired in 2022 as part of the “Big Construction” program, is open for freight transport.
Currently, our company continues to restore the most problematic sections of this route. The first section with a total length of 17 km (the length of the “maps” is 6.3 km) has already been completed. Work continues on the second section with a length of 24 km (the length of the “maps” is 3.1 km).
Works on the Chernigov bypass were intensified. The structures of the destroyed bridge near Shestovytsia have been completely dismantled and removed – it is planned to start installing new bored piles in the near future.
A temporary detour is being created in the same direction next to another destroyed bridge near the village of Bilous (157 km of the M-01 highway).
Dismantling work on the bridge over the Desna near Pirogovka (route P-65) has been completed.
On the N-27 highway, a bridge near Kiselyvka has been dismantled, project work is underway.
The war continues, but work on restoring traffic on the roads of Chernihiv region cannot be postponed “for later”. Normal logistics is one of the working conditions of enterprises and the social sphere of the region. That is why the task has been set today – to restore traffic on all the main highways of the region.