The bridge over the Trubizh River on the M-03 Kyiv-Kharkiv-Dovzhansky highway has been fully opened to traffic

Over 150 artificial structures were destroyed in Ukraine during the war. The first of them have already been restored. And our company is the leader in infrastructure reconstruction!

In the fall, we opened traffic on both lanes across the bridge in Stoyanka (route M-06, Irpin River). Having restored the most important and powerful transport corridor connecting Kyiv with EU countries. Simultaneously with Stoyanka, work continued on the reconstruction of the bridge over Trubyzh (route M-03 Kyiv-Kharkiv). The right-hand drive was completed in November. This week we fully opened the bridge to traffic.

This is a truly historic, significant event. Our company has connected the West and the East of the country again! The bridge over Trubizh near the village of Borshchiv on the Kharkiv highway was also blown up at the beginning of the war to prevent the enemy from breaking through to the capital. The length of the building is 93 meters. Three running structures were destroyed and two were damaged. Back in April, our company arranged a temporary detour and began dismantling the emergency structures. The bridge was completely dismantled.

The first stage of reconstruction: installation of bored piles, supports, grates, nozzles, crossbars and other structures, installation of reinforced concrete beams (8 units for each span).

Next stages: reinforced monolithic slab 22 cm thick, waterproofing, two layers of asphalt concrete, monolithic sidewalks with anti-slip and waterproof coating, metal barrier fence, handrail fence. The drainage system has been restored.

The new bridge was built wider, so the approaches to it at a distance of 150 meters had to be replaced. Complete disassembly of the road surface was carried out on the adjacent sections (53 m). On the rest (97 m), milling and installation of the leveling and top layer of asphalt concrete was performed. ❗️So, “Automagistral-Pivden” did not just restore the old bridge, but built a modern infrastructural object, which now meets the parameters of first-category highways (only part of the piles remained from the old bridge).

 Please note that the project is not completed today! The temporary detour built in the spring is being analyzed, and other related works are being carried out. ❗️The commissioning of the bridge is planned for next year.