The construction and reconstruction project of the Chisinau-Giurgiulesti highway in Moldova is fast approaching completion
The construction of two bridges at 151 and 170 kilometers has been completed
The 2-kilometer section of the reconstruction has been completed
Excavation has been completed on a 3-kilometer section of the new construction
On the last section, it remains to arrange the road structure and perform a number of auxiliary works.
Currently, works on strengthening the slopes and installation of the drainage system are ongoing. The last stage of the construction of the 3-kilometer section will start approximately at the beginning of September.
We are moving according to the schedule! It is planned to finish the work in October this year.
We would like to remind you that work on the 85-kilometer M3 highway “Kyshiniv-Dzhurdzhulesti” began in 2019. Our company has even built a production base in the city of Vulcanesti, where an asphalt concrete plant and a soil mixing plant are located. In 2022, 7 kilometers of the road will be built “from scratch”, an additional 4 kilometers will be expanded and auxiliary road construction will be planned.
The project in Moldova involves the creation of the accompanying infrastructure of the highway – new, modern car pavilions, lighting, footpaths, parking lots.
Currently, the first section of the project (km 96+800 — km 151+200) with a length of 55 km, including nine bridges, is almost completed.
On two other sections (km 151+200 — km 171+290) and km (179+650 — km 190+750), where reconstruction is planned, work is still ongoing.
Since the intensification of work in April of this year, almost fifty units of equipment have been additionally moved to Moldova. Currently, more than 150 units of specialized and automotive equipment are involved in the project.