R-34 Road Reconstruction in Moldova: Work Underway on 10 km of Road Sections

The implementation of our new project in Moldova has gradually reached full scale. The number of machines on site has been increased to 151, with 283 workers currently involved in the project.
Works are being carried out on one of the two lanes, while traffic on the other lane is organised under a temporary traffic management scheme. To minimise congestion, the length of each active work section is limited to 500–600 metres.
There are currently almost 20 such work sections, with a combined length of 10 km.
All types of works are underway – from milling and construction of drainage layers to the placement of the lower asphalt concrete layer.
As with any major road project, R-34 has its own specific features. In this case, they are related to the second pavement structure type.
The reconstruction project provides for two types of pavement structures.
1. Type 1 – complete replacement of the pavement structure:
☑ milling;
☑ removal of the existing road base;
☑ soil stabilisation with cement (M-20);
☑ construction of two crushed-stone drainage layers (0–63 mm);
☑ construction using cold recycling technology of a cement-treated crushed-stone mix (35%) with the addition of reclaimed milled material (65%);
☑ construction of two asphalt concrete layers (6 cm and 4 cm).
2. Type 2 – combined pavement structure
This option involves partial replacement of the pavement structure and is applied where the bearing capacity of the existing base meets the required standards. In this case, the existing pavement is milled, while the underlying base is retained.
The second type includes:
☑ a 20 cm crushed-stone layer (0–63 mm);
☑ a cement-treated mix incorporating milled material;
☑ two asphalt concrete layers.
A completely new pavement structure of Type 1 is constructed only on the road shoulders, as the carriageway itself needs to be widened to meet the required standards.
However, once milling is carried out, it becomes clear that the existing base is not always in satisfactory condition. This requires amendments to the design documentation, which involves a specific approval procedure.
In addition, the actual need to relocate local utility networks differs significantly from what was originally anticipated.
Despite these challenges, the project is progressing rapidly.
🚩
PROJECT INFORMATION
In August 2025, Automagistral-Pivden and Moldova’s National Road Administration signed a contract for the reconstruction of a 42-km section of the R-34 road leading to the port of Giurgiulești. The section runs between the cities of Cahul and Cantemir along the border with Romania.
Read more about the project
In many locations, the R-34 shows significant deterioration not only of the pavement but also of the underlying road structure. Road markings and safety barriers are missing. Travelling along the road is therefore not only uncomfortable but also unsafe.
The reconstruction of the R-34 is important not only for the development of local communities, but also for improving logistics connections between Moldova and the EU.
The project includes:
🚩 widening the road and reconstructing the pavement, upgrading intersections and access roads to agricultural land and residential properties;
🚩 construction of 6 bridges;
🚩 construction of sidewalks, lighting, safety barriers, drainage systems and utilities, among other works.
A few figures illustrate the scale of the project:
☑ more than 500,000 m³ of earthworks;
☑ more than 375,000 m² of cold recycling;
☑ more than 100,000 tonnes of asphalt concrete to be used for the new pavement.