Completion of the H-31 Highway
Completion of the H-31 Highway: Laying the Base and Binder Asphalt Courses Using the Vögele Super 2100-3 Paver and Vögele MT 3000-2 Material Feeder
Last week, we showed the construction of the final base layer—cement-treated crushed stone aggregate—on the first 800-metre section adjacent to the tunnel-type underpass designed for agricultural vehicles.
Now it’s time for asphalt paving.
The asphalt mix is supplied from the company’s MARINI TOP TOWER 3000 asphalt plant, with a production capacity of 240 tonnes per hour.
For paving operations, we are using the flagship Vögele Super 2100-3 asphalt paver together with the Vögele MT 3000-2 PowerFeeder. The material feeder ensures a continuous supply of asphalt mix to the paver, preventing material segregation, temperature fluctuations, and pavement defects. It also significantly increases paving efficiency—a 25-tonne dump truck is unloaded in just 60 seconds. This technology delivers a perfectly smooth pavement surface without construction joints or surface irregularities.
The first section will be completed this week. Work on the cement-treated crushed stone base and asphalt pavement will then begin on the next three sections, covering a total length of 2.8 km.
PROJECT BACKGROUND
Construction of the second phase of the project – a 30-kilometre section extending from the Dnipro–Donbas Canal to the border with Poltava Region – was suspended after the outbreak of the full-scale war.
As a result, traffic has continued to use the existing route – a narrow, deteriorated road passing through local communities.
The condition of the existing road has become critical and it has long required complete reconstruction.
In 2021, our company completed a substantial portion of the works on the second construction phase:
Considering the substantial amount of work already completed, it is now possible to make every effort to partially open the second construction phase of the N-31 highway to traffic before the end of the year, although certain traffic restrictions will remain in place.
Construction activities have therefore resumed. The company is currently:
PROJECT INFORMATION
The new construction of the N-31 expressway between the Dnipro–Donbas Canal and the border with Poltava Region includes:
• construction of 14 engineering structures, including agricultural underpasses, monolithic tunnels connecting local communities, grade-separated interchanges, and overpasses;
• relocation of existing utility networks;
• construction of two pavement foundation layers using slag aggregate;
• construction of a crushed stone–sand mixture (CSM) base layer;
• construction of a cement-treated crushed stone–sand mixture (CTCSM) base layer;
• construction of a three-layer asphalt concrete pavement;
• construction of stormwater treatment facilities;
• installation of stormwater drainage systems;
• installation of variable message signs and weather monitoring stations;
• installation of lighting at interchanges;
• construction of access roads and junctions;
• installation of safety barriers;
• installation of road signs;
• application of road markings;
• landscaping of adjacent areas, including the planting of approximately 5,500 trees.
• installation of Weigh-in-Motion (WIM) systems on both carriageways;
• installation of noise barriers.
The pavement structure will incorporate nearly half a million tonnes of slag supplied by metallurgical plants in Dnipropetrovsk Region.
The most technically challenging element of the project is the construction of an almost 600-metre viaduct crossing the meandering Oril River within a protected nature reserve.