M-09 Highway: Construction of the New Pavement Structure Has Begun on the Final Sections!

❗️M-09 Highway: Construction of the New Pavement Structure Has Begun on the Final Sections!
The M-09 highway rehabilitation project, being implemented by our company, involves the reconstruction of 33.4 km of road, from the village of Volia-Vysotska to the border crossing point. The works are being carried out in stages to minimize disruptions to traffic.
During the first phase, construction activities covered sections with a total length of approximately 26.7 km. On almost all of these sections, we have already completed:
✅ the cement-treated crushed stone aggregate base course (C7, M20 cement-treated);
✅ the 10 cm lower asphalt layer using coarse-grained asphalt concrete.
🚩The 6 cm intermediate asphalt layer made of fine-grained asphalt concrete has already been completed on nearly 23 km of the highway.
🚩We are also actively placing the 5 cm wearing course using Stone Mastic Asphalt (SMA-15).
At present, all asphalt paving works have been fully completed on a section of almost 2 km.
⏩️As work is completed on some sections, we are able to begin milling the remaining sections where reconstruction of the pavement structure has not yet started.
❗️By the end of this year, we plan to complete all asphalt paving words across the entire project.