M-09 Highway: Construction of the New Pavement Structure Has Begun on the Final Sections!
The M-09 highway rehabilitation project, being implemented by our company, involves the reconstruction of 33.4 km of road, from the village of Volia-Vysotska to the border crossing point. The works are being carried out in stages to minimize disruptions to traffic.
During the first phase, construction activities covered sections with a total length of approximately 26.7 km. On almost all of these sections, we have already completed:

the cement-treated crushed stone aggregate base course (C7, M20 cement-treated);

the 10 cm lower asphalt layer using coarse-grained asphalt concrete.

The 6 cm intermediate asphalt layer made of fine-grained asphalt concrete has already been completed on nearly 23 km of the highway.

We are also actively placing the 5 cm wearing course using Stone Mastic Asphalt (SMA-15).
At present, all asphalt paving works have been fully completed on a section of almost 2 km.

As work is completed on some sections, we are able to begin milling the remaining sections where reconstruction of the pavement structure has not yet started.

By the end of this year, we plan to complete all asphalt paving words across the entire project.