The first routine road repair project in the Sumy region since the start of the full-scale invasion!

default
default
default
default
default
default
The first routine road repair project in the Sumy region since the start of the full-scale invasion!
Automagistral-Pivden is carrying out routine repairs on the H-07 Kyiv – Sumy – Yunakivka highway in the Sumy region: milling operations and installation of a new leveling asphalt layer.
Work is underway on two sections:
4.4 km between the villages of Pravdyuky and Korovyntsi.
3 km (sections of 1.1 km, 0.95 km, and 1.05 km) within the settlement of Nedryhailiv and the village of Shtepivka.
These are among the worst sections of the H-07 highway. They had originally been scheduled for rehabilitation back in 2022, but since then only pothole repairs had been carried out. At present, almost the entire pavement consists of patches from previous years.
Two paving crews are working on site, involving 50 workers and 22 pieces of equipment. The works are scheduled for completion by June 1