N-31 “Dnipro – Tsarychanka – Kobeliaky – Reshetylivka”: 150 pieces of machinery are working daily to build the road embankment using 7,000–8,000 cubic metres of sand!

The construction of the road embankment on the second stage of the project requires a huge volume of earth material. We started the works in May, and since then have already placed more than 800,000 cubic metres.

Currently, 7,000–8,000 cubic metres of sand are delivered to the site every day. A massive production and logistics operation is running continuously at the construction site:

14 excavators and 10 bulldozers work in coordination to load, spread and grade the material.

120–130 dump trucks continuously transport the sand.

Water trucks, rollers and other machinery are engaged in earthworks and the construction of access roads.
The strength of Automagistral-Pivden lies in its ability to efficiently organise, control and maintain the uninterrupted operation of this large-scale logistics chain!