N-31 “Dnipro – Tsarychanka – Kobeliaky – Reshetylivka”

❗️N-31 “Dnipro – Tsarychanka – Kobeliaky – Reshetylivka”: 150 pieces of machinery are working daily to build the road embankment using 7,000–8,000 cubic metres of sand!
❗️The construction of the road embankment on the second stage of the project requires a huge volume of earth material. We started the works in May, and since then have already placed more than 800,000 cubic metres.
🚚Currently, 7,000–8,000 cubic metres of sand are delivered to the site every day. A massive production and logistics operation is running continuously at the construction site:
✅ 14 excavators and 10 bulldozers work in coordination to load, spread and grade the material.
✅ 120–130 dump trucks continuously transport the sand.
✅ Water trucks, rollers and other machinery are engaged in earthworks and the construction of access roads.
The strength of Automagistral-Pivden lies in its ability to efficiently organise, control and maintain the uninterrupted operation of this large-scale logistics chain!