Vita-Poshtova Interchange: the monolithic deck has been fully completed!
On the M-05 Kyiv–Odesa highway, the formwork has been removed and the height restriction for oversized vehicles has been lifted.
Currently, we are:
• constructing monolithic sidewalks, abutment walls and transition slabs;
• installing safety barriers, kerbs and drainage channels;
• completing other associated works that will allow the viaduct to be opened for construction traffic.
We are preparing for the installation of expansion joints, waterproofing of the deck and asphalt paving.
Completion of the second part of the interchange – the U-turn “horseshoe” – will allow drivers travelling towards Kyiv to safely turn towards Boyarka.