M-09 Highway: Working 24/7
Works at the site are now being carried out in two shifts!
At night, we mostly lay the base course made of C7 crushed stone-sand mixture stabilized with M20 cement, along with the binder layer of coarse-grained asphalt concrete (10 cm). During the day — the wearing course made of SMA-15 (5 cm).
The objective is to complete asphalt paving works across all sections by the end of the year.
Even before the war, the EBRD conducted a road safety audit, an economic feasibility analysis, as well as an environmental and social assessment. In 2020, a financing agreement was signed between Ukraine and the bank for a number of projects, including the major repair of the M-09.
During the war, the project became even more critical: traffic load increased while the road surface condition degraded.
The M-09 major repair project, implemented by our company, involves the reconstruction of 33.4 km of road (from the village of Volia-Vysotska to the border crossing point). We are executing the works in stages to avoid obstructing traffic.
What the project entails: